Advanced Product Quality Planning (APQP) is no longer just an automotive requirement; it is the gold standard within the aerospace sector. More businesses are adopting APQP to minimise risk, reduce “Cost of Poor Quality” (CoPQ), and stabilise production before the first part even hits the shipping dock.
While APQP can seem daunting for SMEs, its most powerful tool—the Control Plan—is a scalable asset that makes good business sense for any organisation.
What is a Control Plan in APQP?
According to AS9145 (the aerospace standard for APQP), a Control Plan is a documented description linking manufacturing process steps to key inspection and control activities.
The primary intent is to manage both design characteristics and process variables to ensure consistent product quality. Whether used as part of a full APQP rollout or as a standalone tool, it is the ultimate “shield” against process variation.
Why Your Business Needs a Control Plan
A common misconception is that Control Plans must be exhaustive, listing every minor risk. In reality, an effective plan focuses only on the Key Characteristics (KCs) and Critical Items (CIs) identified during your risk assessment.
Core Benefits:
- Preventative Quality: Shifts the focus from “detecting” defects to “preventing” them through error-proofing.
- Reduced Variation: Identifies input variables (process) to stabilise output variables (product).
- Waste Elimination: Directly reduces scrap, rework, and “firefighting” costs.
- Customer Confidence: Provides a transparent roadmap of how you guarantee their specifications are met.
When to Create or Update Your Plan
The Control Plan is a living document. It should be initiated in Phase 3 (Process Design) of APQP and refined in Phase 4 (Product & Process Validation). You should refresh your plan when:
- Implementing a new manufacturing process.
- Following a process change or equipment upgrade.
- A non-conformance or “escaped” defect is identified.
- Significant risks are mitigated/identified in the PFMEA.
Essential Inputs for a Robust Control Plan
To build an effective plan, you need data. If you are already certified to AS9100, you likely have these inputs ready:
- Process Flow Diagram (PFD): The map of your journey.
- PFMEA (Process Failure Mode and Effects Analysis): Highlights the high-risk areas that require control.
- Key Characteristics (KCs): Often identified on engineering drawings or through a DFMEA.
- Measurement System Analysis (MSA): Ensures your gauges are actually capable of measuring the tolerance.
- Lessons Learned: Past failures from similar product families.
The Three Pillars of a Control Plan
A standard Control Plan (referencing the IAQG Supply Chain Management Handbook) is divided into three distinct segments:
1. The Process & Equipment
- Process Step: Matching the numbering in your Process Flow Diagram.
- Machine/Tools: Specific IDs for jigs, fixtures, or CNC centres used.
2. Characteristics
- Product Characteristics: The physical features (dimensions, finish) on the drawing.
- Process Characteristics: The “knob settings”—temperature, pressure, feed rate, or torque—that influence the product.
- Classification: Identifying if a feature is a Critical Item (CI) or Key Characteristic (KC).
3. Methods & Reaction
- Evaluation Technique: What tool are you using? (e.g., Calipers, CMM, or Go/No-Go gauges).
- Sample Size & Frequency: Are you checking 1 in 10, or is it 100% inspection?
- Control Method: How is data recorded? (e.g., SPC Charts, Checklists, or Error-proofing).
- The Reaction Plan: This is crucial. If a part is out of spec, what happens? The plan must include segregation, correction, and supervisor notification.
Pro Tip: Reference AS13006 for specialised guidance on selecting the best Process Control Methods for aerospace applications.
Summary Table: Control Plan vs. PFMEA
| Feature | PFMEA | Control Plan |
|---|---|---|
| Purpose | Identify what could go wrong. | Define how we keep it right. |
| Focus | Risk and Severity. | Monitoring and Measurement. |
| Outcome | Risk Mitigation Actions. | Process Stability & Reaction Plans. |